Developing Projects
Cost share projects can take 12-24 months or longer from the time the application is received to the time when the project is completed and installed on the landscape.
All projects listed on this page are in the development process or are "in progress". Site visits have been completed and "before" photos recorded. Surveys were done on October 31, 2023. Construction plans will be completed in late 2023/early 2024 and some contractors have shown their interest in bidding on the projects.
Depending on final numbers of our 2024 funding, there may be additional money available for another project. We typically fund three projects at about $10,000 in cost share funding for each.
All projects listed on this page are in the development process or are "in progress". Site visits have been completed and "before" photos recorded. Surveys were done on October 31, 2023. Construction plans will be completed in late 2023/early 2024 and some contractors have shown their interest in bidding on the projects.
Depending on final numbers of our 2024 funding, there may be additional money available for another project. We typically fund three projects at about $10,000 in cost share funding for each.
2023-01 - Lake Nokomis
Estimated Cost: $20,000.00
A survey for this project has been scheduled for late October, 2023. One hundred feet of frontage is scheduled to be restored.
2024-01 - Bridge Lake
Estimated Cost: $25,000.00
Plans for this project include removal of the timber seawall and replacement with rock riprap. Installing a native planting buffer for a minimum of 6 feet behind the rock is also planned. Possible soil-filled bags may need to be placed if rock height does not meet with top height of timber. Survey is planned for late October.
2023-02 - Pelican Lake
Estimated Cost: $20,000.00
Plans for this project include removal of the concrete pad and retaining wall. Rock riprap will be added to follow the contour of the bank. Design plan will be created in late 2023/early 2024.