Completed Projects
Projects on this page include designs that were completed and
on the landscape in 2020 and 2021.
2020-01 - Diamond Lake
Estimated Cost: $8,000
Completed November 11, 2021
The areas in this location were seeded in late fall with sedge seed: porcupine sedge, bottlebrush sedge and fox sedge. Shear force was used as a protective layer in this approach to the lake. The seed will grow in and cover all the matting in a couple of years.
In these two (above) "After" photos, biodegradable logs were placed all along the shoreline (yellow arrows) and planted with woolly fruit sedge; common lake sedge; pointed broom sedge; bottlebrush sedge; and fox sedge.
Most of the area in front and surrounding the Rain garden in the photo above, were planted with no mow grass.
2020-04 - Two Sisters
Estimated Cost: $23,498.00
Project completed: July, 2021
This project consisted of soil-filled, vegetated bags, vegetated rock rip rap and hundreds of ground cover plants and shrubs. The project protected 100' of shoreline.
2019-01 - Wisconsin River
Estimated Cost: $40,000.00
Completed: May, 2020
Root Wads were cut and placed on the property. Most were roughly 10-12 feet in length not including the root wad. Each one was chain sawed to a point for easier installation. Click on each photo to make it larger.
They were installed at the river's edge in October of 2019. Some were inserted horizontally and some were pushed in vertically. Once in place, they were secured.
They were installed at the river's edge in October of 2019. Some were inserted horizontally and some were pushed in vertically. Once in place, they were secured.
Please note that the bag wall was not part of the original cost share design. The homeowner wanted additional protection for the river bank and he and the contractor constructed the wall outside of the cost share program. Native plantings were installed in the Summer of 2020 to complete the cost share portion of the project. See where those plantings were installed by clicking the PLANTINGS button.
2019-02 - Lake Nokomis
Estimated Cost: $19,000.00
Completed: 9/25/2021
NOTE: Cost Sharing on this project was done on the rip rap and plantings behind the rocks only. The bag wall was NOT within the project scope for this property.
2019-03 - Lake Tomahawk
Estimated Cost: $30,533.73
Completed: August, 2021
2019-04 - Hancock Lake
Estimated Cost: $14,814.00
Completed: June, 2021
Remove existing patio blocks between timber seawall and upland timber wall. Remove seawall. Place rock rip rap at the shoreline.